Below is communication from DC Public Library’s Jaspreet Pahwa to the ANC commissioners and myself regarding Lamond-Riggs Library construction:
Thank you for your ongoing support of the Library project. Here is a quick update on construction progress from your Library rebuild and what to expect in the weeks ahead.
Construction progress update:
- The building has been demolished and debris hauled off.
- Building Permit received Feb 19, 2021.
- Soil borings under the footprint of the old building ahead of foundation work complete
What to expect in the weeks ahead?
- Construction will continue within the permitted hours of 7:00 AM to 7:00 PM Monday through Saturday.
- All work will continue to take place within the enclosed construction fence.
- Deep foundation work will be the major activity over the next month. This work will have construction noise associated with it.
- Vibration monitoring equipment is onsite and all readings to date are well within the threshold; alarms are set to alert if vibration approached near the limit of the safe thresholds.
- Following the completion of the deep foundation work, typical concrete foundation work will commence.
- There will be additional excavators as well as concrete trucks & pumps onsite
- Trucks will still enter and exit the site via South Dakota Avenue into the construction enclosure from Kennedy St.
- All trucks will be completely stationed within the site enclosure to limit the disruption to adjoining South Dakota, Kennedy & Jefferson Streets.
- Underground utility, electrical, and plumbing work is slated to overlap foundation work.
- The sidewalk on South Dakota, Jefferson St & Kennedy St. will continue to remain open for the foreseeable future.
- Consigli Construction is taking all necessary measures to run a safe operation, and as with all construction projects, construction-related noise will be part of the process as the team builds your new library.
As shared previously, as the Library’s Design & Construction lead, I will continue to send updates your way and remain available to answer any technical questions that arise.
Any general questions you receive from the community can be directed to Library’s Community engagement liaison Martha Saccocio at her email: Martha.Saccocio@dc.gov.
Any time-sensitive Construction Safety Issues can be reported to Consigli Construction Superintendent- Michael Davis at 202.570.3375.
Here are a few shots of the building completely gone and soil boring equipment onsite: