Lamond-Riggs Library Construction Update 4/15/2021

From Lamond-Riggs Library Friends

Lamond-Riggs Library construction progress update 4/15/2021:

·  All (151) deep foundation piers have been completed.

·  Construction equipment for deep foundations has been demobilized

·  Post deep foundation site re-grade is complete.

·  Offsite Steel fabrication is complete.

·  Temporary utility coordination is underway.

·  As you may recall, from design presentations, the large (Bradford pear) tree closest to the building informed the design concept and the footprint of the new building. As shown in the design phase diagram below, this tree was intended to remain and was safeguarded during demolition. Following the removal of the building, the previously hidden root structure has been under evaluation by Arborist, Urban Forestry, & DDOT and unfortunately as of this week, they all agreed that the tree is a safety hazard and needs to be removed. 

o In consultation with DDOT, an expedited tree removal permit has been filed.

o A distinct mature tree is planned to be transplanted in the proximity of the old tree to keep the design intent intact.

o The exact location and species for the new replacement tree are under consideration and will become clear following ongoing consultation with Urban Forestry & DDOT. 

What to expect in the weeks ahead?

  • Construction will continue within the permitted hours of 7:00 AM to 7:00 PM Monday through Saturday.
  • To make up for the lost weather days, the library has directed Consigli to work Saturdays.
  • All work will continue to take place within the enclosed construction fence.
  • Typical concrete foundations (above the completed deep foundations) are slated to start in the upcoming week and related site work will continue through the month of May.
  • Underground utility, electrical, and plumbing work has commenced
  • Excavators will remain onsite and concrete trucks & pumps, will be onsite during pour days.
  • Trucks will still enter and exit the site via South Dakota Avenue into the construction enclosure from Kennedy St.
  • Coordination of utility work in streets is underway, and an update will follow to share the traffic control plans and dates of the work. 
  • All trucks will be completely stationed within the site enclosure to limit the disruption to adjoining South Dakota, Kennedy & Jefferson Streets.
  • Underground utility, electrical, and plumbing work is slated to overlap foundation work.
  • The sidewalk on South Dakota, Jefferson St & Kennedy St. will continue to remain open for the foreseeable future. 
  • Consigli Construction is taking all necessary measures to run a safe operation, and as with all construction projects, construction-related noise will be part of the process as the team builds your new library.

Any general questions you receive from the community can be directed to Library’s Community engagement liaison Martha Saccocio at her email: Martha.Saccocio@dc.gov.

Any time-sensitive Construction Safety Issues can be reported to Consigli Construction Superintendent- Michael Davis at 202.570.3375

4 responses

  1. So sad about the tree! It’s such a beauty, especially in spring, and will be sorely missed.

    Any update on the temporary library service/location? Between COVID and construction, there’s been no library service for the neighborhood for over a year!

    • Sadly, the Lamond-Riggs Interim Library is too small to open during the Covid-19 pandemic. We are one of several libraries in this same position such as the Deanwood, Northwest One, Parklands-Turner, Rosedale and the Lamond-Riggs and Southwest Interim libraries. None will probably reopen until the Covid-19 guidelines are lifted by the Mayor.
      Hopefully, the pandemic restrictions will be lifted sooner than later.

      • Thanks. Bowser announced earlier this week that Deanwood and Southeast libraries would reopen on May 3 (and the renovated Southwest library on May 6). That prompted me to wonder again when our community’s needs will be addressed and what effort, if any, the city is making.

  2. It’s good to be rid of one more invasive Bradford pear! Hopefully the replacement will be something more appropriate to this part of the world.

Leave a reply to Josh Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.