Due Today August 15: Comments on DDOT South Dakota Avenue Corridor Safety Project

[Ed. Note: Republishing this post because today, August 15, is the last day to submit comments for the first phase of engagement on the South Dakota Avenue Corridor Safety Project. There is still time to provide feedback to DDOT to make sure we address speeding through street design, get needed improvements at key intersections in the neighborhood, and work towards developing a corridor that safely supports multiple means of moving around the neighborhood outside of just private vehicles.]

DDOT is looking at ways to address safety issues on South Dakota Avenue from Bladensburg Road NE to Riggs Road NE.

Let DDOT know what you think about what is needed along the corridor by completing this questionnaire and providing information on this public input map (where you can identify important changes you’d like to see at specific intersections like more visible crosswalks, better pedestrian accommodations, etc).

Councilmember Parker earmarked funds in the FY2024 budget for a road diet on the corridor. While much of the media attention has been erroneously focused on bike lanes, the alternatives for a road diet include potential parking lanes where there are none currently, as well. It is worth taking a look at the presentation slides to see all of the alternatives, including how DDOT could potentially address traffic diversion to side streets or address congestion through, for example, signal timing.

Most agree speeding is a problem on South Dakota. There is a relatively low volume of vehicles during off-peak hours, which makes the wide road ripe for speeding. There are too many crashes and near misses. People feel unsafe crossing the street. Too many pedestrians have been injured or killed walking along the corridor. People want to be able to safely walk and bike to points along the corridor. Everyone wants the situation to be addressed. The question is how to get there.

Project Scope

DDOT is going to study the entire corridor, examine three concepts for a road diet, select one concept, and design and build the concept on one portion of the corridor. DDOT will also make spot improvements at certain intersections, which is why it is really important to indicate on the map where improvements are needed. DDOT plans to start construction on the southern end (near Bladensburg) because they state that is where there is highest need.

DDOT is going to study three options for the corridor.

Option One: 3 lanes with full-time parking

Option one would have three lanes with parking on each side of the street.

  • Maintains one lane in each direction
  • Uses curbside space for full-time parking
  • Center space can be left turn lanes or pedestrian islands depending on needs

(Currently, no parking is allowed on South Dakota except for limited parking on the west side of South Dakota between Galloway and Ingraham (soon extending to Kennedy). A couple of churches closer to the southern end of the corridor use a lane for parking on Sundays.)

Option Two: 3 lanes with parking and two-way protected bike lanes

Option two would have three lanes with parking and a two-way protected bike lane:

  • Maintains one travel lane in each direction
  • Uses curbside on one curb face for protected bike lanes
  • Uses opposite curb for parking
  • Center space can be left turn lanes or pedestrian islands depending on need

Option Three: 3 lanes with protected bike lanes in each direction

Option three would have three lanes with protected bike lanes in each direction.

  • Maintains one lane in each direction
  • Uses curbside space for protected bike lanes
  • Center space can be left turn lanes or pedestrian islands depending on needs

Project Timeline

DDOT plans to gather data, explore concepts, and gather input before holding a second round of public meetings in fall 2024, having a third round of public meetings in winter 2024/2025, beginning work on design plans in spring 2025, and finally starting construction just on the southern end in summer 2025.

Though DDOT is going to focus the limited construction money on the southern end of the corridor to start, please take the time to provide input to DDOT about neighborhood issues through this public engagement effort. In particular, I think that highlighting problematic intersections and needed safety, mobility, and access improvements in the neighborhood on the public map will be useful given that we know there are no immediate plans for bike lanes on SDA in the neighborhood.

Contacts

Questions may be sent to the project team:

Sayra Molina, Corridor Safety Team
sayra.molina2@dc.gov

Christine Mayeur, Associate Director, Traffic Safety Engineering
christine.mayeur@dc.gov

Dalando Baker, Ward 5 Community Engagement Specialist
dalando.baker@dc.gov