The District Department of Transportation (DDOT) published a newsletter on the Met Branch Trail (MBT) Fort Totten to Takoma extension. You can sign up to receive the newsletter and email updates at https://forms.office.com/r/p4heFT9diL. This issue covers the general timeline and provides links to a few project resources, such as the pre-construction meeting recording and FAQs. It also provides information about Phase 1 construction staging (previously described in this post). The project website is https://mbt-forttotten-takoma.ddot.dc.gov.
Project Timeline

Phase 1: Summer 2023 to Fall 2025
Construction Begins Fort Totten Metro Station Parking Area to South Dakota Avenue NE
Phase 2: Winter 2023 to Winter 2024
Construction on South Dakota Avenue NE to McDonald Place NE to Blair Road NW
Construction on East side of roadway
Phase 3: Winter 2024 to Spring 2025
Construction on Blair Road – Oglethorpe Street NW to Aspen Street NW
Construction on East side of roadway
Phase 4: Spring 2025 to Summer 2025
Construction on Blair Road NW – Oglethorpe Street NW to Aspen Street NW
Construction on West side of roadway and Sandy Spring Road NW
Phase 5: Summer 2025
Construction on Blair Road NW – Oglethorpe Street NW to Aspen Street NW and Sandy Spring Road NW
Construction on roadway medians