The much awaited Sanitary-Sewer tie-in work required to occur outside the construction fence is scheduled for Thursday March 3, 2022. The tie-in point is under the sidewalk on South Dakota Ave. 

Below is a site diagram showing the location of the work -marked in red. The dashed line shows the rerouted path for foot traffic across South Dakota for the stretch between Kennedy and Jefferson St. As always the Construction team will have all required measures in place to enable a safe work zone.

Drawing of utility tie-in location on South Dakota Avenue NE

Any general questions from the community can be directed to Library’s Community engagement liaison Martha Saccocio at her email: Martha.Saccocio@dc.gov.

Any time-sensitive Construction Safety issues can be reported to Consigli Construction Superintendent- Michael Davis at 202.570.3375.