DDOT Ward 5 Open House Updates

Catching up on posts, starting with a few updates from the DDOT Ward 5 Open House held on February 8, 2020.

Metropolitan Branch Trail (MBT) Fort Totten Extension

MBT Extension Brookland to Fort Totten Construction Phases. Source: District Department of Transportation

DDOT’s Metropolitan Branch Trail Project Manager Nannette Bowles shared a few updates about the MBT extension from Brookland to Fort Totten metro station (see handout here). DDOT has finally gotten the necessary easements and rights-of-way from various property owners (Metro, National Park Service, Aggregate Industries) in order to proceed with work on the middle portion (Phases C-D) of the extension, which is also the most complicated part.

As spring approaches, there will be more activity along 1st Place NE by Fort Totten metro station. Replacement of the existing trail alongside the Mamie D. Lee garden and Mary’s Center/Briya/Bridges is nearly done.

After a long pause in posting updates after March 31 of last year, DDOT has started updating the two-week look ahead reports (the weekly progress reports are still a work in progress). They have also revised the timeline again so projected completion is now expected in winter 2020 rather than September 2020. It is entirely possible that this date will change again, but at least it sounds like progress is being made.

Sidewalk on South Side of Galloway Street NE

DDOT’s Ward 5 liaison Kelly Jeong-Olson shared that DDOT and NPS are working to finalize an MOU to construct a trail on the south side of Galloway Street NE between South Dakota Avenue and 4th Street (where there is not a sidewalk). NPS is responsible for design, which DDOT will need to approve. DDOT hopes to have a design finalized by the middle of this year. Once the design is done, DDOT will present it to the community for feedback, likely at an ANC meeting.

This project has been delayed because the original trail NPS designed was not done to proper specification, with NPS designing a 6-foot wide trail rather than a 10-foot wide trail. There will need to be a retaining wall. The design team was also working out how to work around all of the deep tree roots. Stay tuned for an update from your ANC.

Also, folks probably noticed the sidwalk leading from South Dakota Avenue to the bus stop on the south side of Galloway Street was repaved. In addition, the broken sidewalk on Galloway leading to the metro station was finally repaired last week, thanks to attention from two residents, Deborah Grimstead and Robert Oliver.

Crosswalk 400 block of Galloway Street NE

In December 2019, DDOT installed an off-sidewalk parking corral in a portion of the no parking zone near the crosswalk in the 400 block of Galloway Street NE. People still park cars directly behind the crosswalk though so visibility of pedestrians attempting to use the crosswalk is still a problem. At the open house, DDOT said they would investigate placing a second corral behind the crosswalk so that cars are not parked there.

This has been an ongoing issue since fall 2017 when The Modern at Art Place opened. The crosswalk was removed during construction of The Modern. Once the building was completed in 2017, no one thought to put the crosswalk back in and there were conflicting reports about whether DDOT expected the crosswalk to be replaced. It took months for the crosswalk to be replaced and then cars were being parked in the crosswalk and directly surrounding the crosswalk because there was not a curb cut. It took another couple of months for a curb cut to be installed. DDOT piecemealed improvements and repeatedly declined to put in additional signage to indicate that cars should not be parked directly behind the crosswalk.

This is one example of why there needs to be a better method to address the pedestrian safety impacts of development (see also the Ingraham Street NE hawk signal saga). When development projects are completed, there needs to be a more effective way to ensure that the developer has addressed issues in its transportation demand management plan instead of making residents jump through unnecessary hoops to have basic things addressed that should have been addressed during the development and construction process.

The other issue that will need to be addressed here is that a daycare center is scheduled to open in the 400 block of Galloway later this year. Children will undoubtedly be dropped off in cars so there will need to be some accommodation to handle dropoff and pickup around this area that also gets a lot of bus and vehicle traffic.

Path between Gallatin and Galloway Street NE

The saga that is the informal trail between Gallatin Street and Galloway Street near Fort Totten metro station is not something I spoke with anyone about at the open house, but I am putting information about the path here that was shared in a comment by resident (and blog contributor) Robert Oliver on my post with 2020 development updates. Construction of a paved, lit path is scheduled for spring of this year.

Assaults have occurred from time to time on the existing informal path. For decades, residents have requested Congresswoman Eleanor Holmes Norton to get NPS to do something about this informal trail. When the paved path is finally installed, people should still be aware of their surroundings. After all, there is a fully paved trail just west of Fort Totten metro station and people still complain about assaults happening there (not to mention the muggings that happen on sidewalks across the city in broad daylight).

One response

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.