ART PLACE AT FT TOTTEN, LLC
CONSTRUCTION UPDATE NOTICE
Weeks of: September 28, 2015 and October 5, 2015
What to Expect On-Site:
During the next two weeks, the General Contractor, Foulger-Pratt, will continue haul-off of excess soil and receipt of material deliveries requiring heavy equipment accessing the site.
Installation of concrete foundations, waterproofing, sleeves, walls, grade beams, columns and elevated decks continues. Drainage piping and electrical duct banks are being installed, and gravel is being spread out where concrete slabs on grade are now being placed. At garage locations, the slab-on-grade concrete is being placed. The concrete superstructure is working its way across the site and upward. The installation of electrical transformer vaults and conduits along Galloway Street and the future Ingraham Street extension has been completed.
The area of work for Building A is primarily bounded by South Dakota Avenue on the east, the Aventine buildings on the west, Galloway Street on the south, and what will be the new alignment for Ingraham Street on the north.
Lane Closures:
The lane closures to perform new utility installations in South Dakota Avenue and Galloway Street will continue intermittently. This will require up to two lanes to be closed occasionally from the hours of 9 a.m. to 4:00 p.m.
Construction Hours:
Initial construction activity will be taking place Monday – Saturday between the hours of 7 a.m. and 7 p.m.
Contact Information:
For any construction related concerns, please contact Angel Alston, Advisory Neighborhood
Commissioner at 202-556-5958 or email her at angel.alston@anc.dc.gov.
###