Art Place Construction Notice 8/17/2015 & 8/24/2015

ART PLACE AT FT TOTTEN, LLC

CONSTRUCTION UPDATE NOTICE

Weeks of: August 17, 2015 and August 24, 2015

What to Expect On-Site:

During the next two weeks, the General Contractor, Foulger-Pratt, will continue haul-off of excess soil and receipt of material deliveries requiring heavy equipment accessing the site.

Installation of concrete foundations, walls, grade beams, columns and elevated decks continues. Piping and electrical duct banks are being installed and gravel is being spread out where concrete slabs on grade will eventually be placed. The concrete superstructure is working its way across the site and upward. The installation of electrical transformer vaults and conduits along Galloway Street and the future Ingraham Street extension is being completed. Below grade piping and conduit is being installed.

The area of work for Building A is primarily bounded by South Dakota Avenue on the east, the Aventine buildings on the west, Galloway Street on the south, and what will be the new alignment for Ingraham Street on the north.

Lane Closures:

The lane closures to perform new utility installations in South Dakota Avenue and Galloway Street will continue intermittently. This will require up to two lanes to be closed occasionally from the hours of 9 a.m. to 4:00 p.m. Storm drain work in South Dakota Avenue is currently ongoing.

Construction Hours:

Initial construction activity will be taking place Monday – Saturday between the hours of 7 a.m. and 7 p.m.

Contact Information:

For any construction related concerns, please contact Angel Alston, Advisory Neighborhood Commissioner at 202-556-5958 or email her at angel.alston@anc.dc.gov.

###

 