Metro is replacing the bus shelters at Fort Totten Metro station. The first phase will take place April 22 to May 10, 2024 (residents might have noticed preliminary work happening in the area already). The second phase is scheduled to take place May 13 to May 28, 2024.

Below copied from Metro’s website

Fort Totten

The following bus bays at Fort Totten will be receiving new shelters: A, B, C, D, E, F, G, H, J, K
The installation of new bus shelters will occur in two phases at Fort Totten:

Phase 1 – April 22, 2024 – May 10, 2024
Bus bays A, B, C, and K will temporarily close from April 22nd to May 10th to install the new bus shelters. During this timeframe, customers will board their regularly scheduled buses at temporary stop locations:

Phase 1 Relocation Table

Bus bays D, E, F, G, H and J will not be impacted during Phase 1 of the temporary bus stop relocations at Fort Totten.

Customers should be aware that the Kiss & Ride shelter will close temporarily on Wednesday, April 10th and will reopen at the end of Phase 1. Additionally, four parking spaces at the Kiss & Ride will be temporarily unavailable during Phase 1. Sidewalk accessibility will be maintained outside of the Kiss & Ride shelter construction area.

For more information on temporary bus stop locations and accessibility during phase 1, see map.

Fort Totten Vinicity Map_ENGLISH_Phase 1

Phase 2 – May 13, 2024 – May 28, 2024
Bus bay D, E, F, G, H and J will temporarily close. The Kiss & Ride will also be closed during this period. Customers may board buses at temporary stop locations:

Phase 2 Relocation Table

Bus routes serving temporary bus stops T1, T2 and T3 during Phase 1 will be relocated to new temporary bus stop locations during Phase 2. Customers may board buses at temporary stops locations:

Phase 2 Relocation Table_2

Bus bay K and the shelter at the Kiss & Ride will not be impacted during Phase 2 of the temporary bus stop relocations.

Customers should be aware that the Kiss & Ride will be closed during Phase 2.

For more information on temporary bus stop locations and accessibility during Phase 2, see map.

Fort Totten Vinicity Map_ENGLISH_Phase 2

Please plan on additional travel time to access these temporary locations.

Station entrances and exits will not be impacted during construction.

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.